Concrete control joints should be no less than ¼ of the total thickness of the slab (1” deep for a 4” thick pour) and placed no less than 2-3 times (in feet) the thickness (in inches) of the slab (8-12 feet apart for a 4” thick pour).

How big can a concrete slab be without control joints?

Usually, expansion joints should be no farther apart than 2 to 3 times (in feet) the total width of the concrete (in inches). So for a 4 inch thick concrete slab, expansion joints should be no more than 8 to 12 feet apart.

Do I need control joints in concrete slab?

Contraction/control joints are placed in concrete slabs to control random cracking. A fresh concrete mixture is a fluid, plastic mass that can be molded into virtually any shape, but as the material hardens there is a reduction in volume or shrinkage.

Can you fill control joints in concrete?

Once the joint is cut into place, the joint itself is ready to do its job. The joint can then be left as is, sealed, or filled. Sealing or filling should be put off as long as possible to allow the joint to widen, although in practice joints are usually sealed or filled sooner than ideal.

What is the difference between expansion joints and control joints?

Control joints can be isolated within the plane being treated (brick facades, concrete sidewalks) while expansion joints must bisect the entire structure thereby creating a gap throughout all of the building elements—foundation, walls, curtainwalls, plaza decks, parking decks, floors, and roof.

How far apart should the control joints be for a 6 slab?

Rule #5: For better crack control keep the maximum distance between joints in feet at 2 to 2.5 times the slab thickness in inches. For a 6 in. thick slab, the maximum joint spacing should be limited to 12 to 15 ft. Exceeding a joint spacing of 15 ft.

Should you caulk concrete control joints?

Caulking Concrete Cracks and Expansion Joints Caulking the joints and cracks is the best way to stop this from happening. Even expansion joints in your concrete driveway should be caulked. They can be the biggest culprit of water under your slabs.

Should I seal concrete control joints?

Expansion joints must be sealed with a flexible sealant, like QUIKRETE® Self-Leveling Polyurethane Sealant or QUIKRETE® Non-Sag Polyurethane Sealant…or an expansion joint strip, to prevent water from penetrating the joint and deteriorating the sub-base.

What is another name for a control joint?

Control joints, or contraction joints, are sometimes confused with expansion joints, but have a different purpose and function.

Should control joints be filled?

But if left unsealed or unfilled, control joints can become areas for dirt, dust, and debris to collect and cause problems. In food processing, pharmaceutical, and medical facilities, they can become even greater problem areas harboring water, moisture, and threatening bacteria if not properly filled and maintained.

Is it too late to cut control joints?

The timing varies according to local conditions, but typically saw cuts can be done 4 to 12 hours after the concrete has been finished. In hot weather early-entry dry-cut joints are cut 1 to 4 hours after finishing; they’re not cut as deeply as conventional cuts.

What is a control joint in concrete?

Contraction/Control Joints Contraction/control joints are placed in concrete slabs to control random cracking. A fresh concrete mixture is a fluid, plastic mass that can be molded into virtually any shape, but as the material hardens there is a reduction in volume or shrinkage.

When are contraction joints tooled into concrete?

Contraction joints may be tooled into the concrete surface at the time of placement. Joints may be tooled into the surface (first pass) prior to the onset of bleeding or immediately with the first pass of the floating operation. The longer the first pass for jointing is delayed the more difficult it will be to shape clean straight line joints.

When to cut control joints in concrete slab?

1 Control Joints are not intended to stop cracking but rather control cracking 2 It is best to cut joints as early as possible either while finishing with a concrete groover or within 6-18 hours after finishing with a concrete saw. 3 Plan out your control joint spacing 24-36 times the depth of your concrete slab

Why are concrete joints put in concrete?

Often times people think that concrete joints are put in to prevent it from cracking but truth be told, they are simply to create a weak point so the concrete can crack in a more controlled manner.